Question 1
- (Topic 2)
The zero duration of milestones in project planning occurs because milestones:
The zero duration of milestones in project planning occurs because milestones:
Question 2
- (Topic 1)
Which tool or technique is effective in a project in which the deliverable is not a service or result?
Which tool or technique is effective in a project in which the deliverable is not a service or result?
Question 3
- (Topic 1)
A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?
A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?
Question 4
- (Topic 4)
Quality metrics are an output of which process?
Quality metrics are an output of which process?
Question 5
- (Topic 3)
The individual or group that provides resources and support for a project and is accountable for success is the:
The individual or group that provides resources and support for a project and is accountable for success is the:
Question 6
- (Topic 2)
Project management processes ensure the:
Project management processes ensure the:
Question 7
- (Topic 1)
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
Question 8
- (Topic 3)
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?
Question 9
- (Topic 4)
Managing procurement relationships and monitoring contract performance are part of which process?
Managing procurement relationships and monitoring contract performance are part of which process?
Question 10
- (Topic 2)
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
Question 11
- (Topic 3)
Information collected on the status of project activities being performed to accomplish the project work is known as what?
Information collected on the status of project activities being performed to accomplish the project work is known as what?
Question 12
- (Topic 4)
When sequencing activities, what does the common acronym FF stand for?
When sequencing activities, what does the common acronym FF stand for?
Question 13
- (Topic 1)
The Identify Stakeholders process is found in which Process Group?
The Identify Stakeholders process is found in which Process Group?
Question 14
- (Topic 4)
Types of internal failure costs include:
Types of internal failure costs include:
Question 15
- (Topic 2)
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
Question 16
- (Topic 3)
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?