Question 1
Which of the following is a role in the Scrum framework?
Question 2
True or False: The sprint planning is a one-day time boxed meeting divided into two 4-hour sessions?
Question 3
What is the major difference between Product Backlog and Sprint Backlog?
Question 4
Which two of the following are reasons for considering Agile? (Choose two.)
Question 5
The individual, detailed pieces of work that are needed to convert a product backlog item into a working software component or solution are called:
Question 6
What is the primary responsibility of the Scrum Master?
Question 7
When many Scrum Teams are working on a project, what best describes the definition of "done"?
Question 8
What is the primary objective of the daily scrum?
Question 9
The Sprint Goal is selected before the Sprint Backlog is created.
Question 10
The _____ Team is responsible for delivering potentially shippable product increments at the end of each Sprint.
Question 11
The Sprint planning meeting is comprised of how many sections?
Question 12
Which two are properties of the Daily Scrum? (Choose 2)
Question 13
It's come to your attention that some team members feel that Carlos is a negative influence on the team. You can certainly understand why — he believes that everything is doomed. What should you do?
Question 14
True or False: The Scrum Framework encompasses rules or guidelines for architecture?
Question 15
A line in the Agile Manifesto reads, " ________ over following a plan". Please select which option best completes the statement.
Question 16
A line in the Agile Manifesto reads, " _____ and _____ over processes and tools". Please select which option best completes the statement.
Question 17
What is the maximum duration of each Sprint planning meeting section?
Question 18
Select which of the following statements is the most accurate.
Question 19
Which of the following is not a Scrum Master responsibility?
Question 20
A _____ is created during the first half of the Sprint planning meeting and a _____ is created during the second half of the Sprint planning meeting?
Question 21
The Development Team should have all the skills needed to:
Question 22
Who is ultimate responsible for the Product Backlog item estimates?
Question 23
True or False: Scrum is a collaborative effort involving developers and customers in an ongoing dialog?