Want to know Actualtests ASF Exam practice test features? Want to lear more about Exin EXIN Agile Scrum Foundation certification experience? Study Tested Exin ASF answers to Improve ASF questions at Actualtests. Gat a success with an absolute guarantee to pass Exin ASF (EXIN Agile Scrum Foundation) test on your first attempt.
Question 1
Who is the owner of a Sprint Backlog Item during the Sprint Planning meeting?
Question 2
What is meant by the velocity of the team?
Question 3
How does Agile bring predictability to the Planning process?
Question 4
What is the relationship between the Product Backlog, the Release Backlog and the Sprint Backlog?
Question 5
A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points.
Which statement is true regarding this scenario?
Which statement is true regarding this scenario?
Question 6
Who knows most about the progress towards a business objective or a release?
Question 7
Why are estimates expressed in terms of story points difficult to explain outside of the team?
Question 8
What is a Sprint?
Question 9
A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint.
Who may best prepare this report?
Who may best prepare this report?
Question 10
What message can you give to a customer about a key benefit of using Scrum?
Question 11
What is a Scrum-of-Scrums?
Question 12
What should the Scrum Master advise the team to give their main focus, while working in a global distributed team?
Question 13
A large product team features six different teams having ten members each, working on a project that involves four high level features.
How many Product Backlogs should the team have?
How many Product Backlogs should the team have?
Question 14
What is time-boxing?
Question 15
Which statement describes Release Planning?
Question 16
Which is a statement of value as described in the Agile manifesto?
Question 17
During a Sprint Planning session, the team argues about the work estimates for a particular story.
✑ The Product Owner estimates five days.
✑ The Lead Architect estimates two days.
✑ The Scrum Master estimates eight days.
✑ The team member working on it estimates seven days.
What value (in days) should be used for planning?
✑ The Product Owner estimates five days.
✑ The Lead Architect estimates two days.
✑ The Scrum Master estimates eight days.
✑ The team member working on it estimates seven days.
What value (in days) should be used for planning?