Want to know Certleader 1z0-1057 Exam practice test features? Want to lear more about Oracle Oracle Project Portfolio Management Cloud 2019 Implementation Essentials certification experience? Study Vivid Oracle 1z0-1057 answers to Down to date 1z0-1057 questions at Certleader. Gat a success with an absolute guarantee to pass Oracle 1z0-1057 (Oracle Project Portfolio Management Cloud 2019 Implementation Essentials) test on your first attempt.
Free 1z0-1057 Demo Online For Oracle Certifitcation:
Question 1
Which three file-based data imports are available for use in Oracle Project Portfolio Management Cloud?
Question 2
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)
Question 3
You search for resources to fulfill a project resource request but are unable to proceed after receiving the following error message: “The search for resources cannot be completed because the project resource search index is not available. Contact your help desk.”
Identify the cause for this error message. (Choose the best answer.)
Identify the cause for this error message. (Choose the best answer.)
Question 4
Your customer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve. Identify two period options that are available for this purpose. (Choose two.)
Question 5
Your administrator creates maintenance conditions on the Maintain Project Enterprise Labor Resources page. An HCM person is included in a condition with a process order value of 1 and, additionally, there are three other conditions, all with a process order value of 10. Identify two correct statements about the Maintain Project Enterprise Labor Resources process as it relates to process order values. (Choose two.)
Question 6
A project administrator is trying to assign a team member for a project but cannot find the person in the team member list on the Project Definition page. What is the reason for this problem? (Choose the best answer.)
Question 7
Which product offering enables non-exclusive relationships between multiple projects and tasks with contracts and contract lines? (Choose the best answer.)
Question 8
Your customer wants to assign the Net 45 payment term to all sets except for the corporate business unit specific set, which is assigned the Net 15 payment term. At transaction entry, the list of values for payment terms consists of only one set of data: the set that is assigned to the transaction's business unit.
Which reference data sharing method would you set up to meet the customer requirement? (Choose the best answer.)
Which reference data sharing method would you set up to meet the customer requirement? (Choose the best answer.)
Question 9
Identify two attributes for which you can enter budgets that will be considered for Budgetary Controls in Project Portfolio Management. (Choose two.)
Question 10
Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types. Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)
Question 11
Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this. (Choose the best answer.)
Question 12
Which five steps are required for the File-Based Data Import Integration option?
Question 13
Which application would you use to map application roles to external roles? (Choose the best answer.)
Question 14
A consulting services company is currently working on a business transformation project for your client, which spans multiple years. At the first period close, the consulting services company has recognized revenue and the accounting entry created is:
Dr Unbilled Receivables 40,000 Cr Revenue 40,000
At the end of the period, the client is sent an associated bill. What would be the corresponding invoice accounting entry? (Choose the best answer.)
Dr Unbilled Receivables 40,000 Cr Revenue 40,000
At the end of the period, the client is sent an associated bill. What would be the corresponding invoice accounting entry? (Choose the best answer.)
Question 15
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
Question 16
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio Management and Oracle Project Portfolio Management Cloud. (Choose three.)
Question 17
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes in HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers. (Choose the best answer.)
Question 18
Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS. Identify two correct statements about the periodic project labor demand. (Choose two.)
Question 19
Identify two correct role templates available on the Oracle Entitlement Server to generate roles for Project Organization Security. (Choose two.)
Question 20
Which two privileges are assigned to the Project Plan Management duty in Security Reference Implementation? (Choose two.)
Question 21
Identify three correct statements about project types. (Choose three.)
Question 22
Your customer has the following setups on the project plan type that they are using for their projects: Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes Synchronize Task Transaction Dates with Planned Dates = No With these setups in place, you perform the following actions:
* 1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.
* 2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)
Automatically Roll Up Task Planned Dates = Yes Synchronize Task Transaction Dates with Planned Dates = No With these setups in place, you perform the following actions:
* 1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.
* 2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)
Question 23
You have four resources in your organization: P, Q, R, and S. Resource P – Project or resource calendar is active.
Resource Q – Project resource request dates are within the project or resource calendar effective dates.
Resource R – Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S – Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)
Resource Q – Project resource request dates are within the project or resource calendar effective dates.
Resource R – Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S – Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)