Question 1
- (Topic 5)
The cost benefit analysis tool is used for creating:
The cost benefit analysis tool is used for creating:
Question 2
- (Topic 4)
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
Question 3
- (Topic 2)
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Question 4
- (Topic 1)
Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?
Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?
Question 5
- (Topic 1)
In the Initiating Process Group, at what point does the project become officially authorized?
In the Initiating Process Group, at what point does the project become officially authorized?
Question 6
- (Topic 4)
Which item is a cost of conformance?
Which item is a cost of conformance?
Question 7
- (Topic 3)
Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (WBS) to give structure to the decomposition of the scope?
Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (WBS) to give structure to the decomposition of the scope?
Question 8
- (Topic 3)
Which of the following is a component of three-point estimates?
Which of the following is a component of three-point estimates?
Question 9
- (Topic 1)
Which document describes the necessary information to determine if a project is worth the required investment?
Which document describes the necessary information to determine if a project is worth the required investment?
Question 10
- (Topic 3)
Which of the following are inputs to the Plan Procurements process?
Which of the following are inputs to the Plan Procurements process?
Question 11
- (Topic 1)
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
Question 12
- (Topic 1)
Which statement is true about the project management body of knowledge?
Which statement is true about the project management body of knowledge?
Question 13
- (Topic 3)
The traditional organization chart structure that can be used to show positions and relationships in a graphic top-down format is called a:
The traditional organization chart structure that can be used to show positions and relationships in a graphic top-down format is called a:
Question 14
- (Topic 3)
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
Question 15
- (Topic 3)
Which of the following is an output of the Conduct Procurements process?
Which of the following is an output of the Conduct Procurements process?
Question 16
- (Topic 3)
Which illustrates the connection between work that needs to be done and its project team members?
Which illustrates the connection between work that needs to be done and its project team members?
Question 17
- (Topic 1)
PMBOI Guide is a standard that describes:
PMBOI Guide is a standard that describes:
Question 18
- (Topic 3)
Which activity involves ensuring that the composition of a projects configuration items is correct?
Which activity involves ensuring that the composition of a projects configuration items is correct?
Question 19
- (Topic 4)
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
Question 20
- (Topic 1)
Inputs to Identifying Stakeholders include:
Inputs to Identifying Stakeholders include:
Question 21
- (Topic 3)
In complex projects/ initiating processes should be completed:
In complex projects/ initiating processes should be completed:
Question 22
- (Topic 3)
A process is defined as:
A process is defined as:
Question 23
- (Topic 2)
Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?
Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?
Question 24
- (Topic 1)
An element of the project scope statement is:
An element of the project scope statement is:
Question 25
- (Topic 3)
Which of the following will provide the basis for estimating, scheduling, executing, and monitoring and controlling project work?
Which of the following will provide the basis for estimating, scheduling, executing, and monitoring and controlling project work?