Proper study guides for Far out Oracle Primavera P6 Enterprise Project Portfolio Management 8 Essentials certified begins with Oracle 1Z0-567 preparation products which designed to deliver the High quality 1Z0-567 questions by making you pass the 1Z0-567 test at your first time. Try the free 1Z0-567 demo right now.

Free demo questions for Oracle 1Z0-567 Exam Dumps Below:

Page: 1 / 7
Total 84 questions Full Exam Access
Question 1
In your project, cost and work effort is not subject to change. Which duration type should be used?
My answer: -
Reference answer: A
Reference analysis:

Cost and work is here least flexible. If total work effort or fixed costs are most important, choose Fixed Units.
Note: Working with Duration Types Duration type options
Duration type determines whether the schedule, resource availability, or cost is most inflexible when calculations are performed to reflect activity progress. Duration type affects update calculations only when resources are assigned to an activity.
Choose a duration type based on which factor is the most important, or least flexible, in planning your project.
If schedule is most important, choose Fixed Duration and Units/Time or Fixed Duration and Units.
If resource availability is most important, choose Fixed Units/Time.
If total work effort or fixed costs are most important, choose Fixed Units.

Question 2
You are a P6 administrator. You have received a change request against a configured global dashboard, involving the addition of a portlet.
How would you make this change?
My answer: -
Reference answer: C
Reference analysis:

Add the portlet to the Dashboard.
Note:
* Dashboards are created with up to 12 windows of data called Portlets
* Dashboards build upon those analysis tools and present project and portfolio information in a
way that is easy to set up and use. These dashboards can be customized and assigned so that specific users or groups of users can see the same information when they log into the system. Dashboards can be configured to suit individual needs or literally get everyone on the same page.

Question 3
The two global profiles that are hard-coded in the system and cannot be deleted or changed ____ and ____.
My answer: -
Reference answer: DF
Reference analysis:

In addition to any global profiles that you define, P6 provides two predefined global profiles: Admin Superuser and No Global Privileges.
Reference: Application Level Security

Question 4
Select the statement that best describes a global portfolio.
My answer: -
Reference answer: D
Reference analysis:

The drop-down list shows the enterprise project structure by dividing project portfolios into two groups: the "Global Portfolios," which span the entire organization, or "User Portfolios," which are important to the individual project manager.

Question 5
Your customer's project managers are at a very low level of skill/maturity. Your scope of work includes the creation and management of schedule standards, usage of work products and documents, and schedule-variance tracking to improve estimation processes. Work out of scope includes risk and issue management. You have decided to modify a user-interface view for the project managers.
Where do you remove access to risk and issue management?
My answer: -
Reference answer: C
Reference analysis:

We remove these two specific portlets (Risk, Issues) for the Dashboards which are used by the Project Managers.
Note:
* Dashboards are created with up to 12 windows of data called Portlets
* Dashboards build upon those analysis tools and present project and portfolio information in a
way that is easy to set up and use. These dashboards can be customized and assigned so that specific users or groups of users can see the same information when they log into the system. Dashboards can be configured to suit individual needs or literally
get everyone on the same page.

Question 6
This graphic is an example of a ____.
1Z0-567 dumps exhibit
My answer: -
Reference answer: D
Reference analysis:

Example:
\"1Z0-567
Note the checkboxes to the left-hand side of each project. If you uncheck a box, then that project will be removed from the totals displayed. This will also remove that project from the accompanying portfolio view.

Question 7
You are an application administrator. You received a change request to alter the relationship between an EPS node and its associated OBS element.
What would be a prudent course of action to complete before moving forward with this change?
My answer: -
Reference answer: C
Reference analysis:

Users might be affected.
Note: The OBS and EPS are interconnected such that the OBS can be used to apply security roles and access all projects below specific EPS elements.

Question 8
Identify the true statement regarding Schedule Checker.
My answer: -
Reference answer: D
Reference analysis:

Note: The new schedule checker is a tool that assists planners, project managers and the PMO to ensure project plans are built within the guidelines of industry and organizational best practices. The schedule checker performs a 14-point analysis to ensure that activities and dependencies of the project schedule are following desired standards. The schedule checker adheres to the DCMA 14-point assessment check and produces a report that lists all opportunities for corrective action or improvement when aspects of the project schedule fall outside the quality guidelines. The report includes a summary and detailed sections displaying activities falling outside your configured thresholds.
Note 2: The Schedule Checker can be run against one or multiple projects. You can save the thresholds to run again for the project that is open.
The first thing to do is set up the 14 Configurable User Thresholds. See figure below.
\"1Z0-567
Example of output.
Shown below is the top half of the Schedule Check Summary Report.
\"1Z0-567
Reference below the lower half of the Schedule Check report.
\"1Z0-567

Question 9
Identify three types of activity codes.
My answer: -
Reference answer: ACD
Reference analysis:

Note: Global Activity Codes (but not Project-level or ESP-level) that may be created at any time and applied to any project.

Question 10
You are a project manager on a fixed-bid contract. This contract has actually been positioned as a "loss leader" within your company because it is your first contract with this customer. The hope is that you can prove yourself to the customer and win additional business at higher margins down the road. The margins for this contract are very slim.
What would be the best solution to set up in P6 to give you the visibility that you need to minimize the probable financial loss?
My answer: -
Reference answer: B
Reference analysis:

Note: Percent complete
You can also update activity status by entering the completed percentage against it. In the Activity Details screen, you can set the percentage complete for the activity to be one of these three types:
• Duration: It simply calculates the current date versus the start date and planned duration.
• Physical: It requires statusing both resource units (remaining duration or percent complete). This delivers a better representation of progress, but at the cost of requiring greater detail.
• Units: It requires statusing of remaining units. The percent of delivered units compared to planned units drives progress for the activity.

Question 11
Identify three best practice uses of Notebook topics.
My answer: -
Reference answer: ABG
Reference analysis:

A, G: The Project Notebooks portlet is where all the project level notebook topics
are shown in one location. This is especially helpful if your business process is consistently used to show reasons for delays, reasons for change orders, or other significant project communications.
B: Primavera has functions, including Notebook, that enables you to note information associated with an activity, including the reasons associated for establishing a constraint. Note:
* Notebook topics are predefined categories in P6 that help to organize your project notes.
* The notebook topics in Primavera P6 provide team members with a history of all that happened in the project, whether it was a schedule delay due to rain or the breakdown of equipment.
* Notebooks exist not only for Projects, but also can be added to any EPS, WBS, or activity. So, for example, you could create a notebook that describes the purposes and objectives of each WBS element. These notebooks could then be gathered together in a report, which outlines the project by WBS, using the notebooks as summary paragraphs.

Question 12
Identify this window.
1Z0-567 dumps exhibit
My answer: -
Reference answer: C
Reference analysis:

One idea behind Portfolio Analysis in P6 is that it gives you the ability to quickly
make ad-hoc reports. You can quickly change the view and alter what data is displayed and in what form. There are two main kinds of views — scorecards and graphs.
Note: In the context of creating a scorecard: Choosing data to display
There are three areas that you can customize on a scorecard: Columns, Group, and Waterline.
Screenshot (compare to screenshot in the question):
\"1Z0-567
Columns
The columns available are a mixture of Project-level data as well as WBS-level data. You can choose any of these columns on the left-hand side and press the right-arrow to move them to the Selected Columns. On the right-hand side you may re-order the columns by selecting them and using the up and down arrows.
You can choose the default sorting of the data as well. Once on the scorecard screen, you can change the order by simply clicking on the column headers.
The option Show Project Requests determines whether potential projects should also be included in the scorecard.

Question 13
You are an application administrator that has been asked to create a portfolio for an executive. You create the portfolio and have the user test to see whether it meets requirements. However there are a couple of projects that are missing. You look for the portfolio, but it is no longer visible to you. What is the cause of this problem?
My answer: -
Reference answer: C
Reference analysis:

None

Question 14
What are two benefits of designating a resource as inactive?
My answer: -
Reference answer: AE
Reference analysis:

Non-active resources may have left the organization but are not deleted from the system since they may have actual hours. Reference: Field Map for Oracle Primavera
P6 Reporting Database

Question 15
You are a portfolio manager looking for a new portfolio that you manually created for your own use. You have clicked the Group By drop-down list in Portfolios.
What option would you select to quickly find your portfolio?
My answer: -
Reference answer: D
Reference analysis:

Use a filter to display the most recently created portfolios.

Question 16
Select two true statements about the Portfolio Analysis tab in Primavera P6 EPPM.
My answer: -
Reference answer: CE
Reference analysis:

Note: Creating Projects on the Portfolio Analysis Page
Generally, you create projects while working on the EPS page in the Projects section of the application. However, it is also possible to create what-if projects while analyzing portfolios. During the process of evaluating a portfolio, you will often want to capture a new project idea. To create a project on the portfolio analysis page:
1) Click Portfolios.
2) On the Portfolios navigation bar, click Portfolio Analysis.
3) On the Portfolio Analysis page:
a. Make sure you are working with the primary portfolio (at top or left) and not the comparison set for the next steps.
b. In the Scenario list, select a scenario for your analysis.
c. In the View list, select a portfolio view scorecard.
d. In the scorecard, select a row where you want to add a new project.
e. Click Add Project.
4) For the first project you create, if defaults are not already set, the Add Project dialog box appears:
a. Select a default Parent EPS element.
b. Select a default Responsible Manager.
c. Click Select.
5) On the Portfolio Analysis page, click Save. Tip You can change the what-if project\'s Project Status field value on the General detail window of the EPS page. For example, you may later want to change a project from What If to Planned status. Note 2: A portfolio is a collection of projects. Group projects into portfolios so you can easily view data from more than one project at a time.
Reference; P6 EPPM User\'s Guide, Creating Projects on the Portfolio Analysis

Question 17
You are an application administrator. You have been asked by your CEO to simplify the user interface for executives like her who are interested in high level summary information. Identify two ways to satisfy this request.
My answer: -
Reference answer: AE
Reference analysis:

A:
* Customize a toolbar icon. You can individually customize icons in the module. T
* Rather than customizing existing toolbars, you can create custom toolbars that include only the icons you want to display in groups meaningful to you.
E: Customizing menus
The module provides customizable toolbars that enable you to quickly access all available windows, dialog boxes, and associated functionality.
Reference: P6 Professional User\'s Guide, Working with Toolbars and Menus

Question 18
You are an executive that wants to review portfolio data for a high-risk/high-priority group of projects. You go to Portfolios in Primavera P6 Web. However, the data shown is not the correct portfolio. What should you do to correct this problem?
My answer: -
Reference answer: C
Reference analysis:

None

Question 19
You are a portfolio manager. You opened a portfolio and you refreshed the filter. However, some of the projects that were previously in the portfolio are no longer there.
What happened?
My answer: -
Reference answer: A
Reference analysis:

If you choose to update Primavera activities that fall within a filter and choose to add new activities, only activities that meet that filter’s criteria will be added.

Question 20
Identify two available portfolio chart views in Primavera P6.
My answer: -
Reference answer: BC
Reference analysis:

B: Bubble Chart is the most complex and powerful portfolio view.
C: Histograms
Note that this is not a true histogram,
which is a diagram representing a distribution of data. An example of a true histogram would be a chart showing the number of activities completed each month. Histograms in the Portfolio Analysis view are rather a "Relative order of Magnitude" chart presented as an X-Y chart.

Question 21
Select two true statements regarding calendars.
My answer: -
Reference answer: BE
Reference analysis:

B: Project calendars can only be used within a specific project, and can be assigned to activities within the project. A project can also have a default
calendar, which may be either a project calendar or a global calendar.
E: A resource calendar is designed to work for a specific resource. Furthermore, calendars can be assigned to activities and to the resources assigned to that activity.
Note: Calendars describe the time available for project work. A calendar can be defined at three levels: global, project, and resource.

Question 22
You are a program manager for a group of 10+ projects. You actually have a dedicated node for each program, and your owned projects reside under each node. Each program has its own unique requirements for viewing activity data.
You do not want to ask for activity codes that would be visible to the entire organization. Which activity coding solution would serve the needs of the project managers in your programs?
My answer: -
Reference answer: D
Reference analysis:

EPS activity codes can be used only in projects that belong to a specified EPS, including its subordinate EPS nodes, if any.
Note:
* An activity code can be designated as one of three types: Global, EPS, or project.
* Activity Codes can be defined through the Administer | Enterprise Data dialog, where they can be set at the Global, EPS, and Project level. Activity codes help to sort, filter, and group activities.
* Some data can be stored either at the enterprise level, or at the project
level. One such example is activity codes. Some activity codes may be enterprise, perhaps CSI codes to identify the type of work. Others, such as the specific floor in a multi-story construction, are particular to one project and meaningless in others.
Reference: Oracle Primavera P6, What are codes?

Question 23
Identify the true statement regarding administrative functions in P6 R8.
My answer: -
Reference answer: C
Reference analysis:

For P6 Enterprise, all administrative functions are accessed via the web interface.

Question 24
When assigning a user to a user-interface view, deselecting the Allow Editing check box restricts the user’s ability to _____.
My answer: -
Reference answer: B
Reference analysis:

Creating User Interface Views
On the Create User Interface View page, click the Users tab:
Select a user from the Available Users window to assign the user to that view. Click Select to move the user to the Selected Users column.
Select the Allow Editing option to enable the user to edit the contents of their interface view.
Reference; P6 EPPM Administrator’s Guide, Creating User Interface Views

Question 25
Identify the two types of resource calendars in P6 R8.
My answer: -
Reference answer: AE
Reference analysis:

A: Personal calendars are specific to one resource.
E: Shared calendars are often more useful when many resources are working the same schedule.