Want to know Actualtests HPE0-S58 Exam practice test features? Want to lear more about HP Implementing HPE Composable Infrastructure Solutions certification experience? Study Accurate HP HPE0-S58 answers to Up to the immediate present HPE0-S58 questions at Actualtests. Gat a success with an absolute guarantee to pass HP HPE0-S58 (Implementing HPE Composable Infrastructure Solutions) test on your first attempt.
Online HPE0-S58 free questions and answers of New Version:
Question 1
A customer with a 3-frame Synergy composable infrastructure has received a second rack to expand existing composable infrastructure resource pools. The integrator has cabled the management ring as shown.
Which steps should the integrator take to increase availability of this configuration (Choose two.)
Which steps should the integrator take to increase availability of this configuration (Choose two.)
Question 2
A customer using HPE Synergy is unable to access certain VLANs from a single NIC port of a compute module.
Which configuration option in the server profile needs to be verified to ensure that the server profile has the correct configuration?
Which configuration option in the server profile needs to be verified to ensure that the server profile has the correct configuration?
Question 3
How many redundant fabrics are supported in an HPE Synergy frame?
Question 4
What does the hypervisor cluster profile feature of HPE OneView enable the integrator to accomplish?
Question 5
Which technology used in HPE SimpliVity allows a reduction in storage consumption?
Question 6
A customer needs to upgrade an HPE Synergy 12000 frame with an HPE Virtual Connect SE 32Gb Fibre Channel (FC) Module.
Which steps must the integrator take to install the upgrade?
Which steps must the integrator take to install the upgrade?
Question 7
A customer needs to deploy additional management components, such as vCenter Server and HPE Global Dashboard.
According to HPE best practices, how should an integrator deploy these components?
According to HPE best practices, how should an integrator deploy these components?
Question 8
A customer is considering implementing a DRS cluster, but they would like to know how DRS can help to achieve performance goals.
How should an integrator respond?
How should an integrator respond?
Question 9
Match each interconnect device with its appropriate use case.
Solution:
References: https://support.hpe.com/hpsc/doc/public/display?docId=emr_na-c05385134 https://h20195.www2.hpe.com/v2/GetPDF.aspx/c04815127.pdf
Does this meet the goal?
Solution:
References: https://support.hpe.com/hpsc/doc/public/display?docId=emr_na-c05385134 https://h20195.www2.hpe.com/v2/GetPDF.aspx/c04815127.pdf
Does this meet the goal?
Question 10
A customer has the following HPE Synergy solution:
three Synergy frames
two HPE Virtual Connect SE 32Gb Fibre Channel (FC) modules in each time
two HPE Virtual Connect SE 40GB F8 modules
four HPE Synergy 10Gb Interconnect Link Modules
Click the menu option the integrator should use to add more uplinks ports from HPE Virtual Connect SE 32 Gb FC modules to SAN uplink set.
Solution:
References: https://h20195.www2.hpe.com/v2/GetPDF.aspx/c04815258.pdf
Does this meet the goal?
three Synergy frames
two HPE Virtual Connect SE 32Gb Fibre Channel (FC) modules in each time
two HPE Virtual Connect SE 40GB F8 modules
four HPE Synergy 10Gb Interconnect Link Modules
Click the menu option the integrator should use to add more uplinks ports from HPE Virtual Connect SE 32 Gb FC modules to SAN uplink set.
Solution:
References: https://h20195.www2.hpe.com/v2/GetPDF.aspx/c04815258.pdf
Does this meet the goal?
Question 11
An integrator is installing three Synergy frames in different locations for a customer. As part of the installation, the customer requests a single monitoring dashboard that shows the current hardware status, warranty status, and open support cases of all three frames.
Which configuration steps must the integrator perform to provide the customer with this functionality?
Which configuration steps must the integrator perform to provide the customer with this functionality?
Question 12
A customer tries to revert a data volume located on the HPE 3PAR array to a specific snapshot that was taken using HPE Composer, but the process fails. What must an integrator do to fix this problem?
Question 13
A customer has forgotten the password for the HPE Composer managing the customer’s HPE Synergy Infrastructure.
Where can the customer reset the password with the assistance of HPE Support?
Where can the customer reset the password with the assistance of HPE Support?
Question 14
What are valid uses for an IPv4 address pool when configuring an HPE Synergy solution? (Choose two.)
Question 15
A customer wants to expand their existing cluster using the Grow Cluster functionality from OneView for vCenter Server.
Which OS build plan managed by HPE OneView for vCenter Server can the customer use?
Which OS build plan managed by HPE OneView for vCenter Server can the customer use?
Question 16
A customer is using HPE Synergy Composer to manage the compute module and 3PAR volume attachments.
The datastore attached to the VMware servers has run out of space.
What is the most efficient procedure the integrator should follow to extend the volume with minimum effect on the compute modules?
The datastore attached to the VMware servers has run out of space.
What is the most efficient procedure the integrator should follow to extend the volume with minimum effect on the compute modules?
Question 17
A customer has the following configuration: Frame 1
Bay 1 – HPE Synergy 12Gb SAS Connection Module
Bay 2
Bay 3 – HPE Virtual Connect SE 40 GB F8 Module
Bay 4 – HPE Synergy 12GB SAS Connection Module
Bay 5
Bay 6 – HPE Synergy 10 Gb Interconnect Link Module
Frame 2
Bay 1 – HPE Synergy 12Gb SAS Connection Module
Bay 2
Bay 3 – HPE Synergy 10Gb Interconnect Link Module
Bay 4 – HPE Synergy 12Gb SAS Connection Module
Bay 5
Bay 6 – HPE Virtual Connect SE 40Gb F8 Module
How many more frames can the customer add to their Synergy composable fabric? (Note: Enter your answer in the answer field below.)
Solution:
Frame 1 – Bay 2 – HPE Virtual Connect SE 100Gb F32 Module for Synergy (867796-B21)
Frame 1 – Bay 5 – HPE Virtual Connect SE 16Gb Fibre Channel Module for Synergy (779227-B21)
Frame 2 - Bay 2 – Brocade 16Gb/24 Power Pack+ Fibre Channel SAN Switch Module for HPE Synergy (K2Q86A)
Frame 2 – Bay 5 – HPE Synergy 4820C 10/20/25Gb Converged Network Adapter (876449-B21)
Does this meet the goal?
Bay 1 – HPE Synergy 12Gb SAS Connection Module
Bay 2
Bay 3 – HPE Virtual Connect SE 40 GB F8 Module
Bay 4 – HPE Synergy 12GB SAS Connection Module
Bay 5
Bay 6 – HPE Synergy 10 Gb Interconnect Link Module
Frame 2
Bay 1 – HPE Synergy 12Gb SAS Connection Module
Bay 2
Bay 3 – HPE Synergy 10Gb Interconnect Link Module
Bay 4 – HPE Synergy 12Gb SAS Connection Module
Bay 5
Bay 6 – HPE Virtual Connect SE 40Gb F8 Module
How many more frames can the customer add to their Synergy composable fabric? (Note: Enter your answer in the answer field below.)
Solution:
Frame 1 – Bay 2 – HPE Virtual Connect SE 100Gb F32 Module for Synergy (867796-B21)
Frame 1 – Bay 5 – HPE Virtual Connect SE 16Gb Fibre Channel Module for Synergy (779227-B21)
Frame 2 - Bay 2 – Brocade 16Gb/24 Power Pack+ Fibre Channel SAN Switch Module for HPE Synergy (K2Q86A)
Frame 2 – Bay 5 – HPE Synergy 4820C 10/20/25Gb Converged Network Adapter (876449-B21)
Does this meet the goal?
Question 18
Using SSMC, an integrator has added a new CPG on the HPE 3PAR StoreServ array integrated with HPE Composer.
The new CPG is not visible in the HPE Composer.
What must the integrator do to see the new CPG in the HPE Composer console?
The new CPG is not visible in the HPE Composer.
What must the integrator do to see the new CPG in the HPE Composer console?
Question 19
Which component must be deployed at the customer site and is essential for HPE InfoSight for Servers?
Question 20
A customer has two Synergy frames using HPE Virtual Connect and 20Gb satellite modules linked together. What is the maximum number of frames that can be added to this configuration? (Note: Enter your answer in the answer field below.)
Question 21
Refer to the exhibit.
An integrator needs to add an FCoE connection to the server profile, but the FCoE connection type is not available.
What is the likely cause of this issue?
An integrator needs to add an FCoE connection to the server profile, but the FCoE connection type is not available.
What is the likely cause of this issue?
Question 22
Match each HPE server platform with optimal workload.
Solution:
Does this meet the goal?
Solution:
Does this meet the goal?
Question 23
Refer to the exhibit.
A Synergy integrator needs to establish the module cluster links between two master modules, as shown. Which ports can the integrator use for the module cluster links?
A Synergy integrator needs to establish the module cluster links between two master modules, as shown. Which ports can the integrator use for the module cluster links?
Question 24
A customer requires all automated Fibre Channel zones to have a prefix of “SYNERGY” in the automatically-generated zones.
Click where the integrator should change the naming policy.
Solution:
Does this meet the goal?
Click where the integrator should change the naming policy.
Solution:
Does this meet the goal?
Question 25
Refer to the exhibit.
A customer has an HPE Synergy 2-frame configuration, as shown. The customer has a new project and needs to increase the number of compute modules.
What is the maximum number of compute nodes that the customer’s fabric could support?
A customer has an HPE Synergy 2-frame configuration, as shown. The customer has a new project and needs to increase the number of compute modules.